|
|
By Judy Wilson
Pelican staff
Hillsboro Beach –
The town’s $5 million rebuild of its water plant is expected to get
health department approvals and be fully functional late this week.
Tuesday morning, town officials cut a red ribbon marking the official
end of a discussion that began in 2007.
Before the decision to
rebuild, commissioners considered selling the 14-acre water plant tract
on East Sample Road and Dixie Highway and building a reverse osmosis
plant on the grounds of town hall. But costs were prohibitive and
engineers CH2MHill were commissioned to do the rebuild.
As a side
note, the construction of the town’s first water plant in 1970 also had
issues when the commission rejected a $326,160 price tag which had
soared from the original estimate of $215,000. It later voted to go
forward with the project.
As required by the Department of
Environmental Protection, the new plant has enough redundancies to make
it fail-safe, James Rabideau, project manager for CH2MHill, said. Added
were new chemical tanks, filters, pumps, pipes, a testing lab, generator
and electrical room. Security will be maintained at the site by a new
fence and many cameras.
According to Mayor Dan Dodge, plant
supervisor Mike George had been holding the old system together “with
Band-Aids” for a long time. Now much of the work that had been done
manually will be controlled and monitored by computers.
The three
water wells that serve the plant draw from the Biscayne Aquifer in a
zone that shows no signs of salt water intrusion, Rabideau said.
The treated water goes into two storage tanks at the plant and one large one at town hall that holds 750,000 gallons.
Normal water use for the town’s 5,000 residents is between 650,000 and 950,000 gallons a day.
On
peak days it can go over a million gallons, but that amount is way
below the 2.25 million gallons a day the new plant is capable of
producing and which has been allotted to Hillsboro Beach by the South
Florida Water Management District.
As is true of other South
Florida cities, the local water far exceeds the quality offered in
bottled brands. “This meets Environmental Protection Agency standards,”
Rabideau said. “Bottled water only has to meet Food and Drug
Administration standards, and then it could have been sitting in a
warehouse for a year.”
Next on a laundry list of improvements to the water supply is increasing the water pressure.
Initial
estimates to replace the aging pipe system on the barrier island run
around $5 million, but that’s a figure Mayor Dodge is not willing to
confirm.
Nor will he speculate on how to pay for the project. “Let’s
see what the cost is,“ he said. “It will probably be discussed at the
next commission meeting.”
Categories: Headliners
The words you entered did not match the given text. Please try again.
Oops!
Oops, you forgot something.